Duration of the construction site for the Trolleybus in via Pisano reduces from 4 to 2 months
21 March 2024
Nine weeks of works completed in seven days: this is what happened in via Pisano, where of the five phases announced the first three are already on file. A quick construction site whose success was based on the plate tests, with very reassuring results due to the good condition of the existing road foundation, which proved to have characteristics suitable for the transit of the future Trolleybus.
This allowed immediate asphalting in the previously grated portions, complete with horizontal signs already drawn. In the next few hours mechanical vehicles and company employees completely clear the area giving citizens regular traffic until mid-April when, as regards the final interventions on the remaining two segments, the checks with Acqueveronesi are awaited.